Client Name
Ascot Resources
Location
Stewart, BC
Sector
Mining
Project Description
Duration: Ongoing, expected time to complete 26 months
Crew Size: 18
Highlights:
- 2800m3 concrete poured
- Construction of site facilities on large footprint mine site using portable concrete batch plant and rebar fabrication facility
- Modification of existing process plant production facility including large concrete ball mill foundations and mechanical equipment foundations
- Facilitation of cross border travel for crew and shipping of materials/equipment
- Construction of circular clarifier foundation with geotechnical consideration for bedrock bearing