Chip Plant Upgrade Project – Prince George Sawmill

Client Name
Canfor
Location
Prince George, BC
Sector
Forestry

Project Description

Duration: 5 months

Crew Size: 12

Highlights:

  • 2000m³ concrete poured
  • Construction of 30’ tall concrete wall using engineered steel formwork system
  • Complete project on-time and under budget
  • Excavation and backfill for geotechnical ground depth stability for project footprint