Client Name
Teck
Location
Elkford, BC
Sector
Mining
Project Description
Duration: 33 months
Crew size: 50
Highlights:
- 11,000m³ concrete poured
- 30+ large tank bases with on-site batch plant
- Cellular concrete pipe zone fill
- Sandblast & epoxy coating on tank bases
- 700m2 of masonry block walls (300mm wide)
- Supply & install of 1m diameter embedded pipe sleeves
- Monitored heat of hydration using digital thermal couplers
- Mass concrete pour including internal thermal coupler installation and heat of hydration monitoring
- Large 1m x 3m steel pipe embeds installed into mass concrete pour
- Project delivery on schedule and budget during adverse winter weather conditions