Client Name
Newcrest
Location
Dease Lake, BC
Sector
Mining
Project Description
Duration: 14 months
Crew size: 70
Highlights:
- Primary crusher concrete structure base pour 574m³, engineered formwork throughout, 22m high
- 70ft high concrete bent to support a stacker conveyor at the reclaim tunnel
- Installation of conveyor bents, take-up and transfer tower foundations for a 2.5km overland conveyor system
- Installation of a 20m high x 135m long MSE retaining wall
- Installed SAG and ball mill trunion bearing anchor and motor mill bolts
- Grouting of all equipment static and Dynamic equipment bases (cement and epoxy)
- NAG & PAG choke stations for tailings pipeline including a booster station and tailings box
- 120,000 total man hours