Back To Category

Mine Development – Red Chris Mine

Client Name
Newcrest
Location
Dease Lake, BC
Sector
Mining

Project Description

Duration: 14 months

Crew size: 70

Highlights:

  • Primary crusher concrete structure base pour 574m³, engineered formwork throughout, 22m high
  • 70ft high concrete bent to support a stacker conveyor at the reclaim tunnel
  • Installation of conveyor bents, take-up and transfer tower foundations for a 2.5km overland conveyor system
  • Installation of a 20m high x 135m long MSE retaining wall
  • Installed SAG and ball mill trunion bearing anchor and motor mill bolts
  • Grouting of all equipment static and Dynamic equipment bases (cement and epoxy)
  • NAG & PAG choke stations for tailings pipeline including a booster station and tailings box
  • 120,000 total man hours

Project Gallery